New Numbers Are In for What the BEAD/BOB 2 "True-Up" Will Mean
As a follow-up to last week’s NTIA notice new eligible BSLs were on the way, I have received a draft document the NTIA is expected to present state broadband leaders later this week.
9.3.26_NTIA_BEAD_Supplemental_Announce.pdfThe Supplemental Deployment Policy Notice details how states can access “savings” (non-deployment dollars) to cover BSLs that the NTIA says BEAD may have missed. Unserved BSLs that the NTIA is unaware of being covered by other state or federal dollars.
An important point, the NTIA additional locations are ONLY the UNserved (less than 25/3) and does not include locations with less than 100/20 connectivity. Why are they using unserved versus both un- and under-served? Your guess is as good as mine.
With the addition of the NTIA’s remaining count of post-BEAD unserved is as many as 488 thousand BSLs. The actual number could be lessened by either discovery that these locations are currently funded through another program or, in fact, served. A challenge round will need to sort that out.
States will be permitted to allocate up to the (adjusted) number of unserved BSLs multiplied by the average per-location costs.
In all, the preliminary NTIA dataset counts 488,431 locations that will need to be reviewed. Putting the process of BOB 2 on the back-burner for another day, let’s look at the numbers.
A total of $2.4B in non-deployment funds could be deployed for this true-up.
The non-deployment (savings… cough cough) would drop to as low as $20.1B.
The new deployment funding number could reach or exceed the non-deployment total. Woot!
States most in need of funds, according to the draft would be Virginia, Texas, West Virginia, Alabama, and Washington. Again, this is subject to review for other funding sources presently as well as the challenge process.
With the deadline for completion of RDOF projects being the end of 2027, the additional NTIA unserved does NOT make locations eligible that are… at best… unlikely to be built by RDOF because they are still under an enforceable commitment with the FCC.
These are by no means final numbers as each state will receive its list later this week or next week from NTIA for review. But it is interesting to me that it took nine months for non-deployment guidance that only addresses clean-up. A clean-up that will STILL leave as much as $20B in legally appointed non-deployment funds unused and STILL leave locations left behind that are unlikely to be built through straggling RDOF awards.
Proposed timelines suggest that the true-up round could take up to a year. At LEAST nine more months that funds will be in federal government purgatory. Note this doesn’t include NIST in the timeline. The guidance we’ve been looking for may indeed arrive by the end of summer. Only that summer may be 2027.
State-by-state numbers for “BOB 2.”
potential new BSLs.xlsxViews expressed are the author’s own and do not necessarily represent the official position of broadband.io or its affiliates. Contact Doug Adams at doug@broadbandmarketers.com with any comments or questions.